• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • SPECTRA banner
  • Curtiss-Wright banner

BATTLESPACE Updates

   +44 (0)77689 54766
   

  • Home
  • Features
  • News Updates
  • Defence Engage
  • Company Directory
  • About
  • Contact

HIGH VOLTAGE SUCCESS FOR HMS ALBION

March 22, 2006 by

17 Mar 06 A major project to upgrade the high voltage propulsion system, improving the electrical distribution and providing a safer system on Landing Platform Dock Ships (LPDs) Albion and Bulwark, has been designed and delivered on HMS Albion by defence support specialist the DML Group, within an eight month major capability upgrade period. This completed on 10 March, ten days ahead of schedule.

Ingress protection upgrade (from IP23, for water splash or light spray, to IP56 suitable for water leakage and high pressure jetting) was required for a number of high voltage equipment items in the main machinery spaces to avoid the need for special physical and procedural controls and to improve firefighting and damage control capabilities and operational recovery after a fire.

The need had arisen following the change from direct diesel drive to electric propulsion, resulting in 6.6kV equipment in the forward and aft engine rooms and forward auxiliary machinery room needing increased ingress protection. Because it was believed that this would require equipment to be relocated or replaced in order to house it in the requisite sealed enclosures, it was originally thought that the cost would be prohibitive.

DML designers, however (DML being platform design support co-ordinator for the amphibious assault force ships under the Design Support Alliance), challenged assumptions previously made and undertook a detailed high level hazard identification and risk analysis to assess the issue in detail. They established, working in conjunction with the OEMs (Alstom and Trasfor), that the ingress protection could in fact be upgraded in-situ for most of the equipment. An innovative route to achieve this with major cost savings was developed, providing a sound and economically viable solution.

The extensive project involved numerous challenges, given the size of some of the equipment and scale of the work package required within the tight time schedule. Some 18 major electrical propulsion components were worked on.

Much of the equipment also required a cooling system upgrade. In housing the equipment in sealed enclosures to achieve IP56 protection, air cooling was no longer applicable. DML therefore designed and developed an innovative seawater cooling system for these cases, in some instances requiring new systems, in others modification of existing systems. One transformer, weighing 20 tonnes, which could not be modified in its existing location, was repositioned to enable its cooling system to be installed, requiring sizeable access for lifting equipment to be cut in the ship’s vehicle deck.

Further, given the new complexity of the cooling system, DML also ensured that the electronic platform management service (PMS) was upgraded to ensure effective control and monitoring of the cooling systems.

A high voltage synchrodrive and switchboard could not be upgraded to IP56, so a new watertight compartment was designed and built in the forward engine room (effectively a mini-rebuild), with access via a new airlock so that the compartment could form part of the citadel of the ship.

Additionally, the new equipment and system modifications included auxiliary systems, pumps, heat exchangers and fans to harmonic filters, propulsion and ship service transformers, fresh air make up to the new mid switchboard room (MSR), and a local air conditioning unit in the lobby for air treatment in the MSR. New pipework was also required to meet the specified flow and velocity design criteria and re-balancing of the systems.

Work was also undertaken to the electrical system design to support the IP56 upgrade programme, covering all the ship systems involved, including meeting additional power supply requirements, new fire detection arrangements, and new CCTV arrangements. More than 30 electrical systems were affected. Much of the recabling work was undertaken in congested and difficult working conditions.

Moreover, modifications

Primary Sidebar

Advertisers

  • Pythia
  • Teledyne
  • Exensor
  • Visit the Oxley website
  • Blighter
  • SPECTRA
  • Britbots logo
  • Faun Trackway
  • Systematic
  • CISION logo
  • ProTEK logo
  • ProTEK logo
  • ssafa logo
  • IEE
  • EXFOR logo
  • sibylline logo
  • Team Thunder logo
  • Comtech logo
  • GoExporting logo
  • ECHODYNE logo
  • Supercat logo
  • Galvion logo
  • Leonardo DRS logo
  • MTC logo
  • IDC logo
  • DSEI logo
  • DVD2024 logo
  • SDSC logo
  • TELEDYNE FLIR logo
  • VeteranUK logo
  • Matrix Space logo
  • ST Engineering logo
  • EWS logo
  • sentinel photonics logo
  • capua logo
  • Curtiss-Wright logo
  • Brave1 logo
  • Drone Evolution logo
  • AEI Systems logo
  • EOS logo
  • NMSUK logo
  • Openworks logo
  • Sandown Park logo
Hilux UKDSE AARTOS ST Engineering Future Artillery

Contact Us

BATTLESPACE Publications
41 St Georges Drive
London SW1V 4DG

+44 (0)77689 54766

BATTLESPACE Technologies

An international defence electronics news service providing our readers with up to date developments in the defence electronics industry.

Recent News

  • Protek Selected By Dutch Armed Forces

    May 2, 2026
    Read more
  • PARLIAMENTARY QUESTIONS

    May 1, 2026
    Read more
  • MANAGEMENT ON THE MOVE

    May 1, 2026
    Read more

Copyright BATTLESPACE Publications © 2002–2026.

This website uses cookies to improve your experience. If you continue to use the website, we'll assume you're ok with this.   Read More  Accept
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT